How long does a building permit take in Toronto?

Half of the 28,514 permits the City issued over the trailing 12 months came through within 32 days of application. One in ten took longer than 218 days. Which half you land in depends far more on what you are building than on where.

Median wait

32 days

Slowest 10%

218+ days

Permits measured

28,514

Postal areas

98

Wait time by trade

Slowest first. This is the single biggest driver of how long you will wait.

TradeMedianSlowest 10%Permits
New build65 days594 days2,997
Demolition46 days231 days1,505
HVAC35 days235 days4,321
Addition34 days170 days4,757
Pool34 days101 days164
Electrical32 days94 days87
Plumbing32 days257 days5,933
Roofing27 days109 days485
Interior alteration26 days95 days4,129
Deck22 days126 days1,394
Window / Door13 days62 days778

Wait time by postal area

The 98 Toronto postal areas with at least 30 measurable permits, slowest first.

AreaZoneMedianSlowest 10%Permits
M3CNorth York (west)233 days298 days518
M6NWest Toronto & York134 days883 days868
M6AWest Toronto & York67 days611 days483
M1LScarborough60 days279 days331
M9MEtobicoke & Northwest Toronto54 days327 days116
M1MScarborough47 days364 days280
M1BScarborough44 days197 days235
M1KScarborough43 days259 days241
M7AQueen's Park43 days79 days30
M1CScarborough42 days1439 days311
M2MNorth York (east)42 days111 days316
M2RNorth York (east)42 days284 days254
M5ADowntown & Central Toronto42 days340 days315
M8WEtobicoke (south)42 days134 days328
M2KNorth York (east)40 days635 days154
M1SScarborough38 days203 days224
M5TDowntown & Central Toronto38 days210 days267
M6BWest Toronto & York38 days171 days315
M6MWest Toronto & York38 days296 days260
M1JScarborough37 days281 days136
M6LWest Toronto & York37 days231 days149
M1EScarborough36 days171 days283
M1VScarborough36 days125 days171
M3KNorth York (west)36 days123 days101
M4YEast York, East Toronto & Midtown36 days95 days92
M9NEtobicoke & Northwest Toronto36 days378 days170
M1WScarborough35 days143 days134
M3JNorth York (west)35 days230 days147
M9BEtobicoke & Northwest Toronto35 days201 days306
M9WEtobicoke & Northwest Toronto35 days132 days338
M3HNorth York (west)34 days186 days334
M3NNorth York (west)34 days161 days62
M4BEast York, East Toronto & Midtown34 days148 days200
M4PEast York, East Toronto & Midtown34 days150 days241
M9VEtobicoke & Northwest Toronto34 days212 days173
M4WEast York, East Toronto & Midtown33 days168 days377
M5CDowntown & Central Toronto33 days65 days216
M5MDowntown & Central Toronto33 days225 days329
M5VDowntown & Central Toronto33 days114 days431
M9PEtobicoke & Northwest Toronto33 days280 days97
M1NScarborough32 days222 days311
M1PScarborough32 days136 days286
M1TScarborough32 days126 days113
M2NNorth York (east)32 days113 days475
M3ANorth York (west)32 days187 days142
M4SEast York, East Toronto & Midtown32 days153 days386
M5SDowntown & Central Toronto32 days103 days308
M6EWest Toronto & York32 days168 days551
M8ZEtobicoke (south)32 days220 days471
M1HScarborough31 days164 days137
M1RScarborough31 days188 days297
M3BNorth York (west)31 days140 days273
M3LNorth York (west)31 days97 days61
M4AEast York, East Toronto & Midtown31 days112 days110
M4NEast York, East Toronto & Midtown31 days232 days235
M5JDowntown & Central Toronto31 days63 days303
M9CEtobicoke & Northwest Toronto31 days109 days233
M1XScarborough30 days246 days58
M5BDowntown & Central Toronto30 days98 days178
M5EDowntown & Central Toronto30 days65 days79
M6KWest Toronto & York30 days189 days352
M9REtobicoke & Northwest Toronto30 days146 days119
M5GDowntown & Central Toronto29 days110 days261
M5XDowntown & Central Toronto29 days42 days30
M9LEtobicoke & Northwest Toronto29 days96 days91
M4CEast York, East Toronto & Midtown28 days112 days586
M4HEast York, East Toronto & Midtown28 days314 days45
M4MEast York, East Toronto & Midtown28 days276 days402
M5HDowntown & Central Toronto28 days54 days396
M5RDowntown & Central Toronto28 days125 days476
M6CWest Toronto & York28 days151 days375
M6JWest Toronto & York28 days125 days574
M3MNorth York (west)27 days189 days116
M4EEast York, East Toronto & Midtown27 days175 days295
M4VEast York, East Toronto & Midtown27 days74 days247
M6HWest Toronto & York27 days129 days734
M8YEtobicoke (south)27 days96 days233
M2LNorth York (east)26 days94 days134
M2PNorth York (east)26 days158 days93
M4GEast York, East Toronto & Midtown26 days221 days360
M4LEast York, East Toronto & Midtown26 days181 days531
M9AEtobicoke & Northwest Toronto26 days98 days334
M2HNorth York (east)25 days133 days139
M8XEtobicoke (south)25 days105 days138
M4KEast York, East Toronto & Midtown24 days125 days484
M4XEast York, East Toronto & Midtown24 days99 days91
M6GWest Toronto & York24 days125 days594
M6PWest Toronto & York24 days172 days553
M8VEtobicoke (south)24 days165 days365
M2JNorth York (east)22 days85 days225
M4REast York, East Toronto & Midtown22 days96 days184
M5PDowntown & Central Toronto22 days74 days225
M6SWest Toronto & York22 days110 days452
M1GScarborough21 days129 days107
M5NDowntown & Central Toronto21 days70 days190
M6RWest Toronto & York21 days92 days429
M4JEast York, East Toronto & Midtown19 days111 days525
M4TEast York, East Toronto & Midtown16 days93 days202

Common questions

How long does a building permit take in Toronto?
Half of the 28,514 permits issued in Toronto over the last 12 months were issued within 32 days of application. One in ten took longer than 218 days. The wait varies sharply by trade: New build runs about 65 days while Window / Door runs about 13 days.
Which part of Toronto approves permits fastest?
Among the 98 postal areas with enough permits to measure, M4T has the shortest median wait at 16 days and M3C has the longest at 233 days. Area differences mostly reflect what is being built there rather than the office handling it, since project type drives the wait far more than geography.
Why is the median used instead of the average?
Permit waits have a long tail: a small number of complex projects take years and drag the average far above what a typical applicant experiences. The citywide average is 98 days against a median of 32 days. The median is the honest answer to "how long will mine take".

How these numbers are calculated

Each permit’s wait is the number of days between its application date and its issue date, both as recorded by the City of Toronto. We include permits issued in the trailing 12 months, drop records where the issue date precedes the application date, and report a group only when it contains at least 30 permits. Fewer than that and a median is noise.

We publish medians rather than averages. A handful of very large projects take years and pull the average well above what a typical applicant sees: 98 days against a median of 32.

One important limitation: the City’s open dataset covers active permits, so records leave it as projects close out. That means this measures permits currently on record, not a complete historical census, and it is why we restrict the window to 12 months where coverage is most complete. It describes permits already issued and is not a processing commitment from the City. For the official process, see the data sources page.