How long does a building permit take in Toronto?
Half of the 28,514 permits the City issued over the trailing 12 months came through within 32 days of application. One in ten took longer than 218 days. Which half you land in depends far more on what you are building than on where.
Median wait
32 days
Slowest 10%
218+ days
Permits measured
28,514
Postal areas
98
Wait time by trade
Slowest first. This is the single biggest driver of how long you will wait.
| Trade | Median | Slowest 10% | Permits |
|---|---|---|---|
| New build | 65 days | 594 days | 2,997 |
| Demolition | 46 days | 231 days | 1,505 |
| HVAC | 35 days | 235 days | 4,321 |
| Addition | 34 days | 170 days | 4,757 |
| Pool | 34 days | 101 days | 164 |
| Electrical | 32 days | 94 days | 87 |
| Plumbing | 32 days | 257 days | 5,933 |
| Roofing | 27 days | 109 days | 485 |
| Interior alteration | 26 days | 95 days | 4,129 |
| Deck | 22 days | 126 days | 1,394 |
| Window / Door | 13 days | 62 days | 778 |
Wait time by postal area
The 98 Toronto postal areas with at least 30 measurable permits, slowest first.
| Area | Zone | Median | Slowest 10% | Permits |
|---|---|---|---|---|
| M3C | North York (west) | 233 days | 298 days | 518 |
| M6N | West Toronto & York | 134 days | 883 days | 868 |
| M6A | West Toronto & York | 67 days | 611 days | 483 |
| M1L | Scarborough | 60 days | 279 days | 331 |
| M9M | Etobicoke & Northwest Toronto | 54 days | 327 days | 116 |
| M1M | Scarborough | 47 days | 364 days | 280 |
| M1B | Scarborough | 44 days | 197 days | 235 |
| M1K | Scarborough | 43 days | 259 days | 241 |
| M7A | Queen's Park | 43 days | 79 days | 30 |
| M1C | Scarborough | 42 days | 1439 days | 311 |
| M2M | North York (east) | 42 days | 111 days | 316 |
| M2R | North York (east) | 42 days | 284 days | 254 |
| M5A | Downtown & Central Toronto | 42 days | 340 days | 315 |
| M8W | Etobicoke (south) | 42 days | 134 days | 328 |
| M2K | North York (east) | 40 days | 635 days | 154 |
| M1S | Scarborough | 38 days | 203 days | 224 |
| M5T | Downtown & Central Toronto | 38 days | 210 days | 267 |
| M6B | West Toronto & York | 38 days | 171 days | 315 |
| M6M | West Toronto & York | 38 days | 296 days | 260 |
| M1J | Scarborough | 37 days | 281 days | 136 |
| M6L | West Toronto & York | 37 days | 231 days | 149 |
| M1E | Scarborough | 36 days | 171 days | 283 |
| M1V | Scarborough | 36 days | 125 days | 171 |
| M3K | North York (west) | 36 days | 123 days | 101 |
| M4Y | East York, East Toronto & Midtown | 36 days | 95 days | 92 |
| M9N | Etobicoke & Northwest Toronto | 36 days | 378 days | 170 |
| M1W | Scarborough | 35 days | 143 days | 134 |
| M3J | North York (west) | 35 days | 230 days | 147 |
| M9B | Etobicoke & Northwest Toronto | 35 days | 201 days | 306 |
| M9W | Etobicoke & Northwest Toronto | 35 days | 132 days | 338 |
| M3H | North York (west) | 34 days | 186 days | 334 |
| M3N | North York (west) | 34 days | 161 days | 62 |
| M4B | East York, East Toronto & Midtown | 34 days | 148 days | 200 |
| M4P | East York, East Toronto & Midtown | 34 days | 150 days | 241 |
| M9V | Etobicoke & Northwest Toronto | 34 days | 212 days | 173 |
| M4W | East York, East Toronto & Midtown | 33 days | 168 days | 377 |
| M5C | Downtown & Central Toronto | 33 days | 65 days | 216 |
| M5M | Downtown & Central Toronto | 33 days | 225 days | 329 |
| M5V | Downtown & Central Toronto | 33 days | 114 days | 431 |
| M9P | Etobicoke & Northwest Toronto | 33 days | 280 days | 97 |
| M1N | Scarborough | 32 days | 222 days | 311 |
| M1P | Scarborough | 32 days | 136 days | 286 |
| M1T | Scarborough | 32 days | 126 days | 113 |
| M2N | North York (east) | 32 days | 113 days | 475 |
| M3A | North York (west) | 32 days | 187 days | 142 |
| M4S | East York, East Toronto & Midtown | 32 days | 153 days | 386 |
| M5S | Downtown & Central Toronto | 32 days | 103 days | 308 |
| M6E | West Toronto & York | 32 days | 168 days | 551 |
| M8Z | Etobicoke (south) | 32 days | 220 days | 471 |
| M1H | Scarborough | 31 days | 164 days | 137 |
| M1R | Scarborough | 31 days | 188 days | 297 |
| M3B | North York (west) | 31 days | 140 days | 273 |
| M3L | North York (west) | 31 days | 97 days | 61 |
| M4A | East York, East Toronto & Midtown | 31 days | 112 days | 110 |
| M4N | East York, East Toronto & Midtown | 31 days | 232 days | 235 |
| M5J | Downtown & Central Toronto | 31 days | 63 days | 303 |
| M9C | Etobicoke & Northwest Toronto | 31 days | 109 days | 233 |
| M1X | Scarborough | 30 days | 246 days | 58 |
| M5B | Downtown & Central Toronto | 30 days | 98 days | 178 |
| M5E | Downtown & Central Toronto | 30 days | 65 days | 79 |
| M6K | West Toronto & York | 30 days | 189 days | 352 |
| M9R | Etobicoke & Northwest Toronto | 30 days | 146 days | 119 |
| M5G | Downtown & Central Toronto | 29 days | 110 days | 261 |
| M5X | Downtown & Central Toronto | 29 days | 42 days | 30 |
| M9L | Etobicoke & Northwest Toronto | 29 days | 96 days | 91 |
| M4C | East York, East Toronto & Midtown | 28 days | 112 days | 586 |
| M4H | East York, East Toronto & Midtown | 28 days | 314 days | 45 |
| M4M | East York, East Toronto & Midtown | 28 days | 276 days | 402 |
| M5H | Downtown & Central Toronto | 28 days | 54 days | 396 |
| M5R | Downtown & Central Toronto | 28 days | 125 days | 476 |
| M6C | West Toronto & York | 28 days | 151 days | 375 |
| M6J | West Toronto & York | 28 days | 125 days | 574 |
| M3M | North York (west) | 27 days | 189 days | 116 |
| M4E | East York, East Toronto & Midtown | 27 days | 175 days | 295 |
| M4V | East York, East Toronto & Midtown | 27 days | 74 days | 247 |
| M6H | West Toronto & York | 27 days | 129 days | 734 |
| M8Y | Etobicoke (south) | 27 days | 96 days | 233 |
| M2L | North York (east) | 26 days | 94 days | 134 |
| M2P | North York (east) | 26 days | 158 days | 93 |
| M4G | East York, East Toronto & Midtown | 26 days | 221 days | 360 |
| M4L | East York, East Toronto & Midtown | 26 days | 181 days | 531 |
| M9A | Etobicoke & Northwest Toronto | 26 days | 98 days | 334 |
| M2H | North York (east) | 25 days | 133 days | 139 |
| M8X | Etobicoke (south) | 25 days | 105 days | 138 |
| M4K | East York, East Toronto & Midtown | 24 days | 125 days | 484 |
| M4X | East York, East Toronto & Midtown | 24 days | 99 days | 91 |
| M6G | West Toronto & York | 24 days | 125 days | 594 |
| M6P | West Toronto & York | 24 days | 172 days | 553 |
| M8V | Etobicoke (south) | 24 days | 165 days | 365 |
| M2J | North York (east) | 22 days | 85 days | 225 |
| M4R | East York, East Toronto & Midtown | 22 days | 96 days | 184 |
| M5P | Downtown & Central Toronto | 22 days | 74 days | 225 |
| M6S | West Toronto & York | 22 days | 110 days | 452 |
| M1G | Scarborough | 21 days | 129 days | 107 |
| M5N | Downtown & Central Toronto | 21 days | 70 days | 190 |
| M6R | West Toronto & York | 21 days | 92 days | 429 |
| M4J | East York, East Toronto & Midtown | 19 days | 111 days | 525 |
| M4T | East York, East Toronto & Midtown | 16 days | 93 days | 202 |
Common questions
- How long does a building permit take in Toronto?
- Half of the 28,514 permits issued in Toronto over the last 12 months were issued within 32 days of application. One in ten took longer than 218 days. The wait varies sharply by trade: New build runs about 65 days while Window / Door runs about 13 days.
- Which part of Toronto approves permits fastest?
- Among the 98 postal areas with enough permits to measure, M4T has the shortest median wait at 16 days and M3C has the longest at 233 days. Area differences mostly reflect what is being built there rather than the office handling it, since project type drives the wait far more than geography.
- Why is the median used instead of the average?
- Permit waits have a long tail: a small number of complex projects take years and drag the average far above what a typical applicant experiences. The citywide average is 98 days against a median of 32 days. The median is the honest answer to "how long will mine take".
How these numbers are calculated
Each permit’s wait is the number of days between its application date and its issue date, both as recorded by the City of Toronto. We include permits issued in the trailing 12 months, drop records where the issue date precedes the application date, and report a group only when it contains at least 30 permits. Fewer than that and a median is noise.
We publish medians rather than averages. A handful of very large projects take years and pull the average well above what a typical applicant sees: 98 days against a median of 32.
One important limitation: the City’s open dataset covers active permits, so records leave it as projects close out. That means this measures permits currently on record, not a complete historical census, and it is why we restrict the window to 12 months where coverage is most complete. It describes permits already issued and is not a processing commitment from the City. For the official process, see the data sources page.